Construction Projects
Last Content Update:
Our city is buzzing with a variety of infrastructure and construction projects, ranging from street improvements to water and wastewater upgrades, and from enhancing our parks and trails to upgrading public facilities. These initiatives are all about making our community safer, more accessible, and enjoyable for everyone.
Ever wondered about the construction you're seeing around town? Take a peek at our Interactive Construction Projects Map. It's your go-to guide for all current and upcoming projects, giving you the dirt on what's happening in De Soto!
Road & Sidewalk Improvements
Due to their pavement conditions, the following project sites were selected* for the 2025 in-house Street Maintenance Program:
| Asphalt Project | Work Performed By |
|---|---|
| Cherokee Street into Istas Drive, 4" Overlay | In-House, Street Department |
| W. 95th Street, 3" Overlay | In-House, Street Department |
| Corliss Road, 3" Overlay | In-House, Street Department |
| TBD | Contracted |
| TBD | Contracted |
| TBD | Contracted |
*These projects are budget dependent; if the project was not completed in 2025, they will be the top priority for 2026.
The 2025 annual sidewalk program budget covers small repairs around De Soto, with the largest allocation going towards sections of downtown – Shawnee St., Delaware St., and 84th St.
Water & Wastewater Improvements
Additional 5 miles of sewer lines - including a new pump station - from Astra Industrial Park to the Wastewater Treatment Plant, traveling along Sunflower Road, 95th Street and Kill Creek Rd. to service the Astra and Flint development area.
5-Mile Sewer Printable One Pager
Purpose
Additional wastewater collection lines and a new pump station is needed to handle the new Panasonic battery plant, Astra Enterprise Park, and surrounding area.
A pump station, also known as a lift station, is a crucial part of a sewage system. Its main function is to pump wastewater from a lower to a higher elevation, especially when the gradient of the terrain does not allow for a natural flow.
As the area expands, there is an increased demand for wastewater services. The construction of a new pump station, along with additional sewer lines, will ensure that the wastewater collection system can handle the growing needs of the community. Additionally, by expanding the system, the project will help the city comply with federal and state regulations regarding wastewater management.
Where
The new sewer line will be constructed along...
- Sunflower Rd., between 79th St. and 95th St.
- 95th St., between Sunflower Rd. and Lexington Ave.
- The west side of Kill Creek, from 95th St. southward into the Astra Enterprise Park. (See Map).
When
The project is under construction and is expected to be complete Spring of 2025.
Project Team
- Owner: City of De Soto
- Developer: Panasonic
- Engineer: HDR
- Contractor: Kissick Construction
New sewer lines and a pump station are being constructed to service the Flint Commerce Center. The wastewater collection system expansion includes construction of about 1 mile of new gravity sewer lines and about .5 miles of force main.
Flint Sewer Collection System Printable One Pager
Purpose
This project is needed to accommodate the growth of the Flint Commerce Center and the surrounding area.
A pump station, also known as a lift station, is a crucial part of a sewage system. Its main function is to pump wastewater from a lower to a higher elevation, especially when the gradient of the terrain does not allow for a natural flow.
As the area expands, there is an increased demand for wastewater services. The construction of a new pump station, along with additional sewer lines, will ensure that the wastewater collection system can handle the growing needs of the community. Additionally, by expanding the system, the project will help the city comply with federal and state regulations regarding wastewater management.
Where
The new gravity sewer line will be located along Edgerton Road between K-10 and 103rd Street. The new forcemain will be located along the north side of K-10 from Edgerton Road to Sunflower Road.
When
The project started in October, 2022, and is expected to be completed in Fall, 2024.
Funding
Flint Development
Project Team
- Owner: City of De Soto
- Developer: Flint Development
- Engineer: BCH
- Contractor: To Be Determined
Construction of a new Elevated Water Storage Facility with a capacity of 2 million gallons per day (MGD)
Water Tower Project Printable One Pager
Purpose
The new water tower is being built to ensure that De Soto has a reliable water supply to support new industry and development. As the city grows with residential, commercial, and industrial developments, there is an increasing need for a dependable water supply. The new water tower will provide several benefits:
- Ensuring an adequate water supply for daily use.
- Maintaining reliable water pressure during peak usage times, such as early morning and evenings.
- Providing enough water for emergency situations, such as firefighting.
Additionally, by constructing this new water tower, De Soto will maintain control over its water supply, ensuring that the community is not reliant on external sources for drinking water.
Where
The new water tower will be located on the north side of 103rd Street and east of the
Lexington Avenue intersection. It is north of the Astra Enterprise Park.
When
The new water tower is currently in the engineering design phase, and the anticipated completion time is 2025.
Funding
Panasonic, reimbursed by TIF agreement
Project Team
- Owner: City of De Soto
- Engineer: HDR
- Contractor: Phoenix Fabricators & Erectors
Expansion of the De Soto Water Treatment Plant - located on Astra Parkway. - increasing the capacity from 2 Million Gallons Per Day (MGD) to 8 MGD.
Water Treatment Plant Expansion Project Printable One Pager
Purpose
The purpose of expanding De Soto's drinking water treatment plant is to meet the increasing demand for water. These upgrades will significantly increase capacity, ensuring a sufficient drinking water supply for current customers and future growth in De Soto.
Where
The main project is located in the Astra Industrial Park, at the end of Astra Parkway, but there will also be improvements to the City’s raw water system adjacent to the Kansas River.
When
The feasibility study for water system expansion was conducted in 2022, engineering design for the system expansion occurred in 2023, and construction started February of 2024.
The expansion should be completed by Spring 2025.
Funding
Panasonic, reimbursed by TIF agreement
Project Team
- Owner: City of De Soto
- CMAR (Construction Manager at Risk) Engineer: HDR
- CMAR Contractor: Garney Construction
Expansion of the De Soto Water Treatment Plant - located west of Riverfest Park - increasing the capacity from 1.3 Million Gallons Per Day (MGD) to 3.9 MGD.
Wastewater Treatment Plant Expansion Printable One Pager
Purpose
Expanding our wastewater treatment plant is crucial to accommodate new and future development in the area. This upgrade will not only meet the growing demand for wastewater system services in De Soto but also ensure compliance with federal and state regulations.
Additionally, pump stations, also known as lift stations, are a crucial part of a sewage system. Its main function is to pump wastewater from a lower to a higher elevation, especially when the gradient of the terrain does not allow for a natural flow.
As the area expands, there is an increased demand for wastewater services. The construction of a new pump station will ensure that the wastewater collection system can handle the growing needs of the community.
Where
The project is located at the current De Soto wastewater treatment plant site on near 79th and Sunflower Road.
When
The engineering and design of the wastewater treatment plant expansion started in October 2022.
Construction began February 2024 and will be completed by Spring 2025.
Funding
Panasonic, reimbursed by TIF agreement
Project Team
- Owner: City of De Soto
- Progressive Design Build: Burns & McDonnell, CAS Construction
- Owner Representative: GBA
Park & Facility Improvements
City Hall renovation project is currently in progress.
Purpose
The purpose of the project is to accommodate additional city personnel to better serve the De Soto community. As De Soto grows, additional staff are needed to provide the services required to maintain our infrastructure. The second story of city hall will be renovated for new personnel and expanded services, including space for the EDC and Chamber.
Benefits of renovating the second story of city hall include:
- Cost efficient to house city personnel in an existing building.
- Work efficiency for staff to collaborate and work together to better serve De Soto.
- Meet the office space needs of a growing staff with cost and construction time savings.
- A professional work environment promotes employee retention.
Construction of a 10-foot wide recreational trail along the east side of Sunflower Road, from 91st to 103rd Street.
When
Under design, with a construction start date of Fall 2024
Funding
KDOT Transportation Alternative Grant Program
Project Team
- Owner: City of De Soto
- Engineer: Affinis
- Contractor: TBD
Construction of De Soto's first City-owned disc golf course at Riverfest Park. This project is revitalizing the longstanding vision for a disc golf course in the Riverfest Park Master Plan.
The Riverfest Disc Golf Course project aims to transform 21 acres within Riverfest Park into a premier disc golf destination. Drawing inspiration from successful courses like Cedar Ridge in Bonner Springs and Hobby Hill in Gladstone, our design team envisions a course that is both challenging and picturesque, with iconic holes showcasing the scenic views of the river.
Course Features
- Tournament course with 18 holes
- Two baskets per hole - shorter distance baskets for novice players and longer distance baskets with more difficult flight lines for advanced players
- Practice baskets
- Large tee pads, at least 6’ x 12’
- Quality, multi-lingual tee signage and info board
- Benches throughout the course
- Lost-disc drop box
The new Sunflower Fire Station will support the city's growth, strengthen emergency response, and prioritize firefighter health and safety. Centrally located, it will replace De Soto’s current 80-year-old facility, ensuring the community is served by a state-of-the-art facility built for the future.